Cleanroom Desing Criteria
Ay Seçiniz
Yıl Seçiniz
1
2
3
4
5
Lütfen üye girişi yapınız!
Cleen Room Design Criteria-EN
1-) Project's Name
1-) PROJECT'S NAME :
2-) Location
2-) LOCATION :
3-) Purpose
3-) PURPOSE :
4-) Contact Name
4-) CONTACT NAME :
5-) Phone
5-) TELEPHONE :
6-) E-mail
6-) E-MAIL :
7-) What's the requested dimensions of the cleanroom ? (length * width * height)
7-) What's the requested dimensions of the cleanroom? (length * width * height) :
8-) What's the height of the area which the cleanroom will be built in ?
What's the height of the area which the clean room will be built in ? :
9-) Maximum dimensions of the materials which will get into the room and in-out procedure of the materials ?
Maximum dimensions of the materials which will get into the room and in-out procedure of the materials ? :
10-) Is pass through box requested for material access and exit? How many ? If yes what are the spesifications ? (Dimensions, Hepa filter, UV, Electronic interlock etc.)
Is pass through box requested for material access and exit? How many ? If yes what are the spesifications ? (Dimensions, Hepa filter, UV, Electronic interlock etc.) :
11-) What's the classification class of the cleanroom ?
What's the classification class of the clean room ? :
12-) What are the physical conditions requested in the cleanroom ?
SUM
°C
What are the physical conditions requested in the clean room ? (SUM) :
%
RH
What are the physical conditions requested in the clean room ? (RH) :
WIN
°C
What are the physical conditions requested in the clean room ? (WIN) :
%
RH
What are the physical conditions requested in the clean room ? (RH) :
13-) What are the physical conditions of the ambient ?
SUM
°C
What are the physical conditions of the ambient ? (SUM) :
%
RH
What are the physical conditions of the ambient ? (RH) :
WIN
°C
What are the physical conditions of the ambient ? (WIN) :
%
RH
What are the physical conditions of the ambient ? (RH) :
14-) What are the physical conditions of the air in the area which the clean room will be built in ?
SUM
°C
What are the physical conditions of the air in the area which the clean room will be built in ? (SUM) :
%
RH
What are the physical conditions of the air in the area which the clean room will be built in ? (RH) :
WIN
°C
What are the physical conditions of the air in the area which the clean room will be built in ? (WIN) :
%
RH
What are the physical conditions of the air in the area which the clean room will be built in ? (RH) :
15-) How many personnel will work in the cleanroom ?
24 :
16-) What's the thermal power of the devices in the cleanroom ?
What's the theremal power of the devices in the clean room ? :
17-) Are there fume cupboards or laminar flow units in the cleanroom ? If yes, what are their locations and capacities ?
Are there fume cupboards or Laminer flow units in the clean room ? If yes, what are their locations and capacities ? :
18-) Is any gas, that harms human health, used or does any gas come out during process in the cleanroom ?If it is, %100 fresh air will be used for air conditioner system.
Is any gas, that harms human health, used or does any gas come out during process in the clean room ?If it is, %100 fresh air will be used for air conditioner system. :
19-)Is any gas or vapor, that must be exhaust, used or does any gas come out during processes in the clean room ? If it is, separated exhaust fans will be used.
Is any gas or vapor, that must be exhaust, used or does any gas come out during processes in the clean room ? If it is, separated exhaust fans will be used. :
20-) Will any flammable matters be used during processes in the clean room ? If yes, materials must be ex-proof.
Will any flammable matters be used during processes in the clean room ? If yes, materials must be ex-proof. :
21-) Will there be separated area for air handling unit ?
Will there be separated area for air handling unit ? :
22-) What kind of heater is requested in the air handling unit? (Vapour / Hot water / Electrical heater)
What kind of heater is requested in the air handling unit? (Vapour / Hot water / Electrical heater) :
23-) If vapour or hot water heater is wanted, is there a current heat center and installation in the building ? If yes, can the new air handling unit be fed from this system ?
If vapour or hot water heater is wanted, is there a current heat center and installation in the building ? If yes, can the new air handling unit be fed from this system ? :
24-) What kind of cooler is requested in the air handling unit? (Cold water / Dx)
What kind of cooler is requested in the air handling unit? (Cold water / Dx) :
25-) If cold water cooler is requested, is there current cooling line in the building ? If yes, can the new air handling unit be fed from this system ?
If cold water cooler is requested, is there current cooling line in the building ? If yes, can the new air handling unit be fed from this system ? :
26-) Is there any special request for the air handling units ? (stainless stell surfaces, etc)
Is there any special request for the air handling units ? (stainless stell surfaces, etc) :
27-) The air ducts are standard galvanized steel. Is there anywhere wanted stainless steel ? (304, 316L etc.)
Klima santralinde ne tür bir ısıtıcı var? Sıcak su / dirençli buhar / ısıtıcı ile ısıtıcı Elektrikli ısıtma? Özellikleri? :
28-) Can current building carry the air ducts ? (If not, steel construction must be built)
Can current building carry the air ducts ? (If not, steel construction must be built) :
29-) Automatic control system is standard conventional type. Do you want any system connected to the computer ?
Automatic control system is standard conventional type. Do you want any system connected to the computer ? :
30-) What are the other requests and characteristics for designing the system correctly ?
What are the other requests and charecteristics for designing the system correctly ? :
Send
Your transaction is happening Please wait ..
Bugün
HS
Tarih formatı : gg.aa.yyyy şeklinde girilmelidir
Lütfen geçerli bir ay giriniz
Lütfen geçerli bir gün giriniz
Başlangıç tarihi, bitiş tarihinden küçük olmalıdır. Lütfen kontrol ediniz.
Girmeniz gereken tarih aralığı :
Seçilen tarih bu günden ileri bir tarih olamaz.
Seçilen tarih bu günden geri bir tarih olamaz.
Seçili Saat:
Saat:
Dakika:
Saniye:
Şu an
kapat
Şehir
İlçe
Sadece $extension$ uzantılı dosyalar yükleyebilirsiniz
Dosya boyutu $maxFileSize$kb'dan küçük olmalıdır
Seçiniz
Yükleniyor...
Required fields
Lütfen geçerli bir e-mail adresi giriniz..
Lütfen geçerli bir cep telefonu giriniz..
Lütfen Ürünün Seçilebilir Özelliğini Belirleyin.
Lütfen Ürünün Seçilebilir Özelliğini Belirleyin.
Lütfen ürünün seçilebilir özelliğini belirleyin.
Ekleniyor...
Eklendi.
Ürün adedi rakam ve 0 dan büyük olmalıdır.
Girilen miktar $strSatisKati$ sayısının katları şeklinde olmalıdır. Girdiğiniz miktara en yakın uygun değer düzenlenecektir.
Girilen miktar en az $strMinSatis$ olmalıdır. Girdiğiniz miktar $strMinSatis$ olarak düzenlenecektir.
Girilen miktar en fazla $strMaxSatis$ olabilir. Girdiğiniz miktar $strMaxSatis$ olarak düzenlenecektir.
$strDegisken$ sayısal değer olmalıdır
Şifreniz en az 6 karakterden oluşmalı ve en az 1 sayi, 1 harf içermelidir.
Ad Soyad bölümü en az iki kelime halinde doldurulmalıdır
Lütfen veri girişini Sanal Klavye'yi kullanarak yapınız!
Ad veya Soyad alanı en az 2 karakter olacak girilmelidir.
$strDegisken$ alanı en az $minLength$ karakter olmalıdır.
Yazdır
Kapat
$degisken$ Seçiniz
$degisken$ Yok
$degisken$ Seçin
Uyarı
Tamam
İptal
Ürünler
Kategoriler
Ürünler
Sonuç Bulunamadı