Cleanroom Desing Criteria
Cleen Room Design Criteria-EN
1-) Project's Name
2-) Location
3-) Purpose
4-) Contact Name
5-) Phone
6-) E-mail
7-) What's the requested dimensions of the cleanroom ? (length * width * height)
8-) What's the height of the area which the cleanroom will be built in ?
9-) Maximum dimensions of the materials which will get into the room and in-out procedure of the materials ?
10-) Is pass through box requested for material access and exit? How many ? If yes what are the spesifications ? (Dimensions, Hepa filter, UV, Electronic interlock etc.)
11-) What's the classification class of the cleanroom ?
12-) What are the physical conditions requested in the cleanroom ?
SUM°C
%
RH
WIN°C
%
RH
13-) What are the physical conditions of the ambient ?
SUM°C
%
RH
WIN°C
%
RH
14-) What are the physical conditions of the air in the area which the clean room will be built in ?
SUM°C
%
RH
WIN°C
%
RH
15-) How many personnel will work in the cleanroom ?
16-) What's the thermal power of the devices in the cleanroom ?
17-) Are there fume cupboards or laminar flow units in the cleanroom ? If yes, what are their locations and capacities ?
18-) Is any gas, that harms human health, used or does any gas come out during process in the cleanroom ?If it is, %100 fresh air will be used for air conditioner system.
19-)Is any gas or vapor, that must be exhaust, used or does any gas come out during processes in the clean room ? If it is, separated exhaust fans will be used.
20-) Will any flammable matters be used during processes in the clean room ? If yes, materials must be ex-proof.
21-) Will there be separated area for air handling unit ?
22-) What kind of heater is requested in the air handling unit? (Vapour / Hot water / Electrical heater)
23-) If vapour or hot water heater is wanted, is there a current heat center and installation in the building ? If yes, can the new air handling unit be fed from this system ?
24-) What kind of cooler is requested in the air handling unit? (Cold water / Dx)
25-) If cold water cooler is requested, is there current cooling line in the building ? If yes, can the new air handling unit be fed from this system ?
26-) Is there any special request for the air handling units ? (stainless stell surfaces, etc)
27-) The air ducts are standard galvanized steel. Is there anywhere wanted stainless steel ? (304, 316L etc.)
28-) Can current building carry the air ducts ? (If not, steel construction must be built)
29-) Automatic control system is standard conventional type. Do you want any system connected to the computer ?
30-) What are the other requests and characteristics for designing the system correctly ?
Send